Laying the Foundations
The transformation of Stanmore College is progressing rapidly, with foundation work well underway—a crucial step toward building a state-of-the-art campus.
20th November 2024 – Piling Work Begins

- The piling mat was nearly completed, providing a stable base for heavy construction equipment.
- The piling rig arrived on-site and began installing foundation piles, essential for supporting the new buildings.
6th December 2024 – Piling Work Completed
- The piling rig successfully completed its work and was removed from the site, marking a key milestone in the foundation phase.
Stay updated on our website for the latest developments as we build the future of Stanmore College!